Hi,
I am a relatively new Caliber user; have followed the lead of previous users and created a Project with several Requirement Types. Each requirement type has a complex tree of requirements. Each Requirement Type represents a Requirements document. I need to establish a baseline for each Requirement Type so that each baseline will represent the requirements for a specific revision of the document. It looks like Caliber cannot do this but that each document should be its own project; it appears that baselines are assigned or attached to projects. Is this correct?
What can I do to retain the tree of requirements that I have, with the requirements tag/id numbers already assigned, but set up a baseline so that this version of each requirement type can be saved?
Can I move a Requirement type to its own project? Can it retain the tag/id numbers?
Thanks.
Scott FIne